November 10, 2020

2 Min Read
marionlandfill.png

Marion County has awarded SCS the planning, designing, permitting, bid phase services, construction quality assurance (CQA) services, and construction contract management for the approximately 50-acre baseline landfill cell No. 3 closure. The County sought a firm specializing in solid waste, with landfill closure experience in Florida to provide the required design and permitting services, and with the in-house capability to conduct the construction quality assurance (CQA) services required during construction. The entire project is estimated to take three years to complete, with construction spanning multiple rainy seasons.

Weather-related issues during closure construction are one of the critical factors to address. An overly aggressive contractor could strip too large of an existing vegetative area, try to place too much protective cover material over the barrier layer system; either can potentially cause significant erosion during rain events.

The County’s concern about CQA is to prevent placing the protective cover material over the newly installed barrier layer system. Should an unqualified contractor replace the protective cover material on the barrier layer, it will increase construction time and increase the potential for damage to the system. This damage is often not found until the contractor has demobilized from the site, and the facility begins to conduct the required surface emissions monitoring. The resulting repairs to the barrier layer are often a cost the owner incurs, not the contractor.

Based on decades of experience designing, building, and operating landfills, the SCS CQA professionals prevent these types of construction mistakes. Working closely with contractors to ensure construction events are thought through to the operations phases while providing recommendations if the construction plan may encounter potential issues.

“Our entire team is excited to have the opportunity to continue serving Marion County, especially with a project of this magnitude and importance to Marion County,” said Shane Fischer, a vice president with the SCS team. “Our professionals are committed to delivering the highest quality engineering and construction services possible for the long-term success of the project.”

Stay in the Know - Subscribe to Our Newsletters
Join a network of more than 90,000 waste and recycling industry professionals. Get the latest news and insights straight to your inbox. Free.

You May Also Like